Monday, November 14, 2011

SC FM maintenance

11-14-11
Mt Pleasant Ward
9hrs worked
2 men

Work performed today:

Replaced damaged ceiling tile
Touch up wood throughout building
Clean up


Tile in Mothers Room where privacy curtain was

                                                    Tile in Mothers Room

                                                       Tile in Mothers Room

                                                           Mothers Room

                                         Tiles have been replaced in Mothers Room

                                       Scratched up chair rail outside Bishops Office

                                           Chair rail outside Bishops Office with stain

                                                         Scratched chair rail

                                                   Above chair rail with stain







All wood (chair rail, pews, rostrum) has been touched up. Tile in Mothers room and 3 tiles in hallways have been replaced. We will do sisal repair and fix the header over the entry way tomorrow. After that, the punchlist will be complete with the exception of paint. Drywall repairs have been done.