Charleston Stake Center 9/8/11
Work performed today:
Finished sanding trim
Stained all trim and backside rostrum panels
Put polyurethane on all trim and panels
Applied first coat of paint to overflow ceiling
Re-finished podium platform
Removed panels from back side of rostrum
New rostrum panels (stain and poly)
Re-finished rostrum platform (will put microphone back tomorrow after it dries)
Trim and panels drying
Overflow floor covered to protect from paint
Overhead fixtures taped to protect from paint
Overflow ceiling before first coat of paint applied
Overflow ceiling after first coat of paint (paint was still wet at time of pic)
Second coat to be applied tomorrow
Tomorrow we will put the rostrum back together, apply second coat of paint, re-attach microphone and clean up in time for Stake Conference