Charleston Stake Center
10 hrs worked today
3 hrs picking up material (3 trips to CK Supply, 1 trip to Home Depot)
1 hour unloading and staging
6 hrs prep work
Work performed today:
Picked up material for ceiling and placed in Cultural Hall
Ceiling prep
Dumpster placed on site for old insulation and tile
R-19 insulation placed in Cultural Hall
Ceiling tile and more R-19 (insulation on top of tile for protection)
Tables placed around material to protect from basketballs (just in case)
Main foyer (walls protected with plastic, paper on floor)
Hallway beside cultural hall (walls protected with plastic, paper on floor)
Main foyer (walls protected with plastic, paper on floor)
Hallway beside Bishops Office (walls protected with plastic, paper on floor)
Tomorrow, we will begin demo of old ceiling tile and insulation and start putting in the new. We will keep good ceiling tiles and put them in the classrooms on that side of the building so that it all matches. We are going to do this in sections so that we don't have every area on that side of the building blocked off for very long. We will have this work completed Thursday
No comments:
Post a Comment