Thursday, September 29, 2011

SC FM maintenance

9-29-11
Charleston Stake Center
8hrs worked today

Work performed today:
New tile and insulation installed in Bishops Office


                                           Old tile removed from Bishops Office

                                               Tile borders and new insulation

                                                              New borders

                                                           New insulation

                                                                     New tile

                                                                 New tile

                                                               New tile

                                                         Furniture put back in place

                                                   Furniture put back in place

                                                      Old tile and insulation




Tile and insulation is complete. We will start back on the Stake PFR punchlist tomorrow

Wednesday, September 28, 2011

SC FM maintenance

9-28-11
Charleston Stake Center
8 hrs worked today

Work performed today:

Completed ceiling tile installation in hallway
Replaced bad ceiling tile in classrooms and hallway at serving area
Cleaned HVAC grilles 108, 109 (punchlist items)


                                                           Dirty grille in 108

                                                      Cleaned grille in 108

                                                        Dirty grille in 109

                                                   Cleaned grille in 109

                                              Dirty tile in 109 (not very visible in pic)

                                                            New tile in 109

                                                    New tile in hallway

                                                         New tile in hallway

                                  Overall pic of north hallway with new tile (complete)




Tomorrow, we will demo and replace tile and insulation in Bishops Office and repair damaged tile in Clerks Office.

Tuesday, September 27, 2011

SC FM maintenance

9-27-11
Charleston Stake Center
10 hrs worked today
Work performed today:

Demo the rest of the old tile and insulation in the hallway beside the Cultural Hall
Put in new insulation and tile in hallway
Worked on punch list items
Clean up

                                               Broken light switch cover in Relief Society room

                                      New light switch cover in Relief Society room

                                            Unsecured HVAC vent in Chapel

                Secured vent to the wall. Chipped out block and secured with Liquid Nails

                                      Loose surface mount light in High Council room

                                    Light in High Council room secured tight to ceiling

                                             Loose door hardware in room 108

                                                  Door hardware tightened at 108

                                             Hallway prep and ceiling tile demo

                                          Old insulation and tile removed from ceiling

                                                    New R-19 insulation in ceiling

                                                 New R-19 insulation in ceiling

                                     New tile in ceiling (hallway is halfway complete)




I noticed on our punchlist that the gutter straps need to be wire brushed and re-painted. There are approximately 450 of these around the building. To make them look new again will require more than wire brushing and painting. They will all need to be sanded, primed and then painted and then the gutters would possibly need to be painted as well. This could take 2 guys up to 2 weeks or more to do this. Please let me know if you want us to proceed with this.

Friday, September 23, 2011

SC FM maintenance

9-22-11
Charleston Stake Center
8hrs worked today

Work performed today:
Installed new ceiling tile in hallway beside Bishops Office, foyer at Chapel and hallway by Cultural Hall


                                                        New tile in hallway by Bishops Office

                    Overall pic of hallway at Bishops Office with new tile and cleaned up

                  Overall pic of foyer: new tile, cleaned up and furniture put back in place

                                     Overall pic of hallway with new tile and cleaned up

                                              Bell in foyer with new tile cut in

                                                   Close up of border in foyer

                                                       Close up of new tile in foyer

                               Foyer with new tile, cleaned up and furniture put back in place



The hallway by the Bishops Office, foyer at the Chapel and 1/3 of the hallway by the Cultural Hall are complete with new tile and insulation. We will be back Monday afternoon to continue the rest of the hallway. This will be finished on Tuesday. I think it would be a good idea to get an HVAC contractor in to look at the unit above the foyer, it is making a humming noise and the condensate lines are wet. I also think it would be a good idea for an exterminator to investigate the rodent issues in the attic. We haven't seen or heard any but have been told by members that they can hear them running in the attic.

Wednesday, September 21, 2011

SC FM maintenance

9-21-11
Charleston Stake Center
12 hrs worked today

Work performed today:
Demo old ceiling tiles and insulation
Put in new ceiling tile and insulation

     Ceiling tile and insulation removed from hallway beside Bishops Office ( FYI, the piece of insulation to the right was removed, I just didn't get a picture)

                                         Ceiling tile and insulation removed from foyer at Chapel

                Ceiling tile and insulation removed from a portion of the hallway beside Cultural Hall

                                                   New insulation in hallway by Bishops Office

                                                            New insulation in foyer at Chapel

                                                                   New insulation in foyer

                                                    New ceiling tile in hallway by Bishops Office

                                                     New insulation in hallway beside Cultural Hall

                          Strong evidence of rodents living in the attic. I think it's squirrels and mice.

We will continue tomorrow. We also noticed condensation on the HVAC lines above the foyer

Tuesday, September 20, 2011

Charleston SC FM

9-20-11
Charleston Stake Center
10 hrs worked today
3 hrs picking up material (3 trips to CK Supply, 1 trip to Home Depot)
1 hour unloading and staging
6 hrs prep work


Work performed today:
Picked up material for ceiling and placed in Cultural Hall
Ceiling prep

                                            Dumpster placed on site for old insulation and tile

                                                        R-19 insulation placed in Cultural Hall

                             Ceiling tile and more R-19 (insulation on top of tile for protection)

                          Tables placed around material to protect from basketballs (just in case)

                                       Main foyer (walls protected with plastic, paper on floor)

                        Hallway beside cultural hall (walls protected with plastic, paper on floor)

                                          Main foyer (walls protected with plastic, paper on floor)  
                             

                          Hallway beside Bishops Office (walls protected with plastic, paper on floor)


Tomorrow, we will begin demo of old ceiling tile and insulation and start putting in the new. We will keep good ceiling tiles and put them in the classrooms on that side of the building so that it all matches. We are going to do this in sections so that we don't have every area on that side of the building blocked off for very long. We will have this work completed Thursday